MANDATORY CRITICAL STAGE INSPECTIONS

Critical stage inspections are required at the following stages of construction.


  • Piers/footings (prior to pouring concrete)
  • Slab (prior to pouring concrete)
  • Stormwater (prior to covering connections)
  • Frame (prior to covering any floor, wall, roof)
  • Wet Areas (prior to covering any waterproofing)
  • Final (after building work has been completed)

Inspections are also required for the following*:

  • Separating Walls (fire/acoustic)
  • Pool steel
  • Swimming Pool Barrier

*Check your Notice of Critical Stage Inspections.

Please provide at least 48 hours notice.